Evaporator / Heater Core & Chiller Assembly and Test Line
Applicable Products
Assembly and testing of HVAC evaporator cores, heater cores, battery cooling chillers, and other heat exchanger cores.
Core Process Flow
Core Assembly → Header Pipe Welding / Press-fitting → Airtightness / Internal Leak Testing → Internal Blockage Detection → Moisture Detection → Visual Inspection → Finished Product Offloading (EOL)
Description
This fully automatic integrated production line is developed for automotive HVAC heat exchange cores (evaporators, heater cores, and water-cooled chillers). It integrates the full process covering core press-fitting, gasket assembly, pipe fastening, vision-based visual inspection, triple composite testing (water circuit internal leak, internal blockage, and moisture), and refrigerant pre-charging stations. Equipped with dedicated testing equipment for heat exchange cores, it ensures full barcode traceability. The modular workstations can be easily separated for standalone use or linked as a complete assembly line, making it ideally suited for high-volume production of heat exchange cores for both ICE and NEV models.



Key Advantages & Highlights
|
3-in-1 Core Testing Unit |
Integrates internal leak, internal blockage, and moisture/humidity testing; completes full-dimensional verification of core sealing and flow performance on a single line. |
|
Flexible Compatibility for Multiple Products |
Integrates internal leak, internal blockage, and moisture/humidity testing; completes full-dimensional verification of core sealing and flow performance on a single line. |
|
Precise Robotic Press-Fitting |
Servo-controlled positioning of core plates eliminates internal blockage caused by assembly misalignment. |
|
Dry and Waterless Processing Technology |
Full-process vacuum leak detection and dehumidification; no residual moisture to corrode the core. |
|
Full-Station Data Acquisition |
Press-fitting pressure, tightening torque, test pressure drop, and leak rates are all bound to the individual part barcode. |
| Modular and Reusable Line Design |
The testing unit can be detached to function as an independent test fixture, adapting to small-batch trial production. |
Core System Specifications Table
|
Applicable Products |
Laminated evaporators, heater cores, and plate-type water-cooled chillers |
|
Standard Cycle Time |
200s / unit; optimizable up to 150s / unit |
|
Control System |
Siemens S7-1500 PLC, 12-inch Industrial HMI |
|
Pressure Control Accuracy |
Press-fitting pressure ±0.8% FS, leak testing pressure ±0.5% FS |
|
Testing Capabilities |
Simultaneous testing of internal leaks, internal blockages, and residual moisture |
| Leak Detection Accuracy |
≤1×10⁻⁴ mbar·L/s |
| Pressure Drop Resolution for Water Circuit Blockage Detection |
0.1kPa |
| Dehumidification Vacuum Level |
≤50 mbar; residual moisture content ≤100 ppm |
| Conveying Method |
Double-speed chain pallet circulation conveyor, RFID pallet traceability |
|
Line Dimensions |
Standard complete line: 52m × 3.8m; single testing unit footprint: 8 m² |
Core Functions and Value in Detail
|
Automated Assembly & Press-Fitting |
6-axis robots pick and place heat exchange plates and gaskets; servo press precisely performs layer-by-layer pressing; torque modules fasten inlet/outlet pipe connectors. Real-time monitoring of the press-fitting force curve ensures automatic alarms and shutdowns upon pressure abnormalities, preventing plate deformation and gasket misalignment. |
|
Vision-Based Cosmetic Defect Inspection |
Industrial cameras scan for core fin deformation, pipe dents, missing gaskets, and weld cracks. AI vision algorithms automatically determine defects, and defective products are automatically diverted and isolated. |
|
3-in-1 Water Circuit Testing |
① Internal Leak Testing: Independent pressurization via dual channels to distinguish internal cross-leaks from external leaks. |
|
Barcode Traceability & Data Management |
Each core is bound to a unique barcode. Assembly pressure, tightening torque, and values from the three tests are permanently stored and integrated with the factory MES for full-chain traceability of material batches, production personnel, and equipment, complying with automotive industry IATF quality control standards. Business Value: The factory leak and blockage defect rate of cores is reduced by 95%; the manual water immersion leak testing process is eliminated; workshop wastewater discharge is completely eliminated; a single production line saves over 800,000 RMB annually in water treatment and labor costs. |
Supporting Services & Delivery Assurance
1.Pre-project: Free process testing for core samples, modular production line layout planning, and 3D rendering output;
2.Lead Time: 70 working days for a standard complete line, and 35 working days for a standalone testing unit;
3.Implementation: In-house trial run with actual materials → Modular logistics and shipping → On-site joint commissioning of piping, vacuum systems, and electrical control → 3-day continuous full-load trial production;
4.Training: Vacuum system maintenance, vision program calibration, pressure parameter tuning, and MES data integration training;
5.After-sales: 1-year warranty for the entire machine, and a 2-year warranty for vacuum sensors and servo presses; 4-hour response time and 24-hour nationwide on-site engineer dispatch; lifetime cost-effective supply of vacuum filter elements and sealing consumables.