Questions buyers ask before they send a drawing
Commercial terms, cycle-time proof, installation abroad, IP protection and documentation — answered the way we answer them in a technical review, not the way a brochure does.
01
Commercial & quoting
A part drawing or 3D model, the CTQs and test specification, target cycle time and annual volume, your existing process flow if there is one, and the plant layout or footprint limit. A short video of the current manual process is often more useful than a written specification.
Five to ten working days for a standard platform configuration. A first-of-its-kind line takes longer, because the process concept has to be worked out before a number is meaningful.
As a fixed-price package covering design, build, software, FAT, shipping preparation, installation and commissioning, with a separate line for spares and training. Optional items such as AGV delivery or extended warranty are quoted separately so they can be removed.
Typically a down payment at order, a milestone payment at design freeze or build completion, a payment at FAT, and the balance at SAT. Exact terms are agreed in the contract and can be aligned with your internal approval process.
Both. Most export projects are handled directly with the end user’s engineering team; where a local agent or integrator is already in place, we work through them with a clear split of technical and commercial responsibility.
02
Technical & line design
Frequently. We survey the existing stations, keep what is serviceable, and design the new stations, conveyor and control architecture around them. The line controller and MES interface are unified even when the hardware is mixed-vendor.
By running the line at our plant with your components and measuring it. Cycle time is measured over a defined run length, and OEE is calculated from availability, performance and quality using the formula written into the acceptance protocol. The result is recorded as part of FAT.
Siemens S7-1500 with PROFINET as standard. Other platforms can be accommodated where a plant standard requires it — the cost difference is mostly engineering time.
Yes. Fixtures, grippers and part-specific tooling are designed and machined in-house, and they are your property at handover, including drawings.
Camera-based presence, orientation and surface inspection are integrated at station level, and robots are used for load, unload and assembly where the cycle justifies it. We select the brand against your plant standard and spares policy.
03
Delivery, installation & support
A single-station cell usually takes 4–5 months from design freeze to FAT. A multi-station line with integrated test runs 7–10 months, depending on part maturity and the number of custom test stations. Installation and commissioning on site adds 3–6 weeks.
Yes. Our engineers travel for installation, commissioning and training, and we can work alongside your local contractors for rigging and utilities. Visa, insurance and travel costs are quoted as a separate item so they are visible.
Remote diagnostics first, usually within 24 hours. If a site visit is needed, we mobilise the field-service team; response time depends on destination and visa lead time, which is why we agree an escalation path in the contract rather than promising a number we cannot control.
A recommended spare-parts list is supplied at handover, split into wear parts, critical spares and long-lead items. Consumables are specified with equivalent part numbers so they can be sourced locally where possible.
Operator and maintenance training are included in the standard scope, delivered at commissioning and repeated at your site if the line is built abroad. Training material is supplied in English.
04
IP, compliance & documentation
We work under NDA from the first technical exchange, restrict the project to a named engineering team, and keep project data on an isolated server. Part-specific fixtures and documentation are your property and are not reused for other customers.
We design to the electrical and safety requirements you specify, and component selection follows the destination market. Formal CE marking or UL listing is issued by the machinery builder of record for the installed line — we will state clearly in the quotation which parts of that scope we cover and which need a local partner.
Electrical schematics in English, I/O list, pneumatic and hydraulic diagrams, spare-parts list, O&M manual, calibration and test records, and the source project files for the control software on request (escrow is available).
This is an English-language export site. Chinese-language company material exists separately; HMI languages are configured per project.
Still missing an answer?
Send the question with your part drawing. An engineer will answer it directly — not a sales assistant with a template.